Client:

Saline Water Conversion Corporation
SINOPEC/CH2MHILL

Total costs:

approx. 540 Mio. EUR

Performance period:

2012 – ongoing

Data/Structures:

  • Total length of transmission pipeline 620 km, 70 bar, steel pipes, diameter 24” to 76”
  • 4 pumping stations
  • Tape-off and tie in stations
  • Reservoirs and terminals, 8 x 140,000 m³, in total 590,000 m³ storage capacity

IBK – services:

  • System engineering and operation philosophy
  • Hydraulic calculation
  • Pipeline engineering
  • Pipeline facilities, drain and vent stations
  • Technical input for procurement of pipeline facilities
  • As-built documentation