Client:

ASFINAG (Authority for Austrian motorways and expressways

Total costs:

approx. €73 million

Year:

1994 – 2004

IBK-services:

  • Routing in the form of an impact and cost-benefit analysis
  • Preparation of the general planning and detailed road project
  • Adapting the preliminary tunnel designs
  • Providing road construction and noise reports for environmental impact statement
  • Preparing road construction project

Data/structures:

  • Total length approx. 5.6 km motorway
  • Ottsdorf/Thurnham underpass, L = 1,940 m
  • Kremsursprung tunnel, L = 1,213 m, bored tunnel
  • PY43 Hinterburg green bridge, L = 225 m
  • PY44 railway underpass, L = 142 m