Client:
ÖBB – Austrian Federal Railways
Total costs:
approx. 4.02 Mio. EUR
Performance period:
2002 – 2007
Data/Structures:
- 11.180 km high performance railway line
IBK-Services:
- Noise-related analyses
- Planning of the authorization procedure § Par. 36 (1) EisbG
- Detail project
- Static-constructive adaptation